Work Progress
Project Updates
Project construction began on March 23, 2026.
The first phase of construction will be between Harness Rd and Bowstring Rd. This construction includes the following improvements:
- New storm line infrastructure (concrete pipe, inlets, and manholes) – Complete
- Raised concrete median islands – In progress
- Edge of road curb line – In progress
- Pedestrian sidewalk and multi-use trail – In progress
- New asphalt roadway with bike lanes – In progress
The second phase of construction will be between Bowstring Rd and Jackson Creek Pkwy. This construction includes the following improvements:
- New storm line infrastructure (concrete pipe, inlets, and manholes)
- Raised concrete median islands
- Edge of road curb line
- Pedestrian sidewalk and multi-use trail
- New asphalt roadway with bike lanes
- New concrete roundabout in front of Lewis Palmer HS
- New street lights along Higby Rd
- New traffic signals in the Jackson Creek Pkwy intersection
Future updates will be posted here throughout the life of construction.