Project Schedule & Milestones
Milestones
Phase 3:
- July 13, 2026 – July 30, 2026 – Bowstring Road east to Cloverleaf Road: Utility Installation & Roadway Improvements
- No intersections will be closed.
- July 30, 2026 – September 25, 2026 – Bowstring Road east to Cloverleaf Road: Utility Installation & Roadway Improvements
- Bowstring Road intersection will be closed.
Phasing is necessary to accommodate traffic from the high school while school is in session.
Project completion is expected by Friday, September 25, 2026 with a ribbon cutting at 10 AM.