Project Schedule & Milestones

Milestones


Phase 1:

  • March 23, 2026 – Early May 2026 – Bowstring Road east to Harness Road: Utility Installation & Roadway Improvements
    • Cloverleaf Road intersection will be closed.
  • Early May 2026 – Early June 2026 – Cloverleaf Road east to Harness Road: Utility Installation & Roadway Improvements
    • Harness Road intersection will be closed.

Phase 2:

  • May 18, 2026 – August 12, 2026 – Jackson Creek Parkway east to Bowstring Road: Utility Installation & Roadway Improvement

Phase 3:

  • August 13, 2026 – Late November 2026 – Bowstring Road east to Cloverleaf Road: Utility Installation & Roadway Improvements
    • Bowstring Road intersection will be closed.

Phasing is necessary to accommodate traffic from the high school while school is in session.

Work will not occur throughout the winter months, and project completion is expected by late November 2026.

For additional project updates, please visit our progress page.