Project Schedule & Milestones

Milestones


Phase 1:

  • Spring 2026 – Harness Road west to Cloverleaf Road: Utility Installation
  • Spring 2027 – Harness Road west to Cloverleaf Road: Roadway Improvements

Phase 2:

  • Summer 2026 – Bowstring Road west to Lewis Palmer HS
  • Spring- Summer 2026 – Lewis Palmer HS west to Jackson Creek Parkway
  • Summer 2026 – Bowstring Road east to Cloverleaf Road

Phasing is necessary to accommodate traffic from the high school while school is in session.

Work will not occur throughout the winter months, and project completion is expected by Spring-Summer 2027.

For additional project updates, please visit our progress page.