Work Progress
Project Updates
Project construction began on March 23, 2026.
The first phase of construction will be between Harness Rd and Cloverleaf Rd. This construction includes the following improvements:
- New storm line infrastructure (concrete pipe, inlets, and manholes) – Complete
- Raised concrete median islands – Complete
- Edge of road curb line – Complete
- Pedestrian sidewalk and multi-use trail – Complete
- New asphalt roadway with bike lanes – Complete
The second phase of construction will be between Bowstring Rd and Jackson Creek Pkwy. This construction includes the following improvements:
- New storm line infrastructure (concrete pipe, inlets, and manholes) – Complete
- Raised concrete median islands – Complete
- Edge of road curb line – Complete
- Pedestrian sidewalk and multi-use trail – Complete
- New asphalt roadway with bike lanes – Complete
- New concrete roundabout in front of Lewis Palmer HS – Complete
- New street lights along Higby Rd – Complete
- New traffic signals in the Jackson Creek Pkwy intersection – Complete
The third phase of construction will be between Bowstring Rd and Cloverleaf Rd. This construction includes the following improvements:
- New storm line infrastructure (concrete pipe, inlets, and manholes) – Complete
- Raised concrete median islands – In progress
- Edge of road curb line – Complete
- Pedestrian sidewalk and multi-use trail – In progress
- New asphalt roadway with bike lanes – In progress
- New concrete roundabout at Bowstring Rd intersection – Complete
- New street lights along Higby Rd – In progress
Future updates will be posted here throughout the life of construction.