Project Schedule & Milestones
Milestones
Phase 1:
- Fall 2025 – Harness Road west to Cloverleaf Road
- Spring 2026 – Cloverleaf Road west to Bowstring Road
Phase 2:
- Summer 2026 – Bowstring Road west to Lewis Palmer HS
- Spring- Summer 2026 – Lewis Palmer HS west to Jackson Creek Parkway
Phasing is necessary to accommodate traffic from the high school while school is in session.
For additional project updates, please visit our progress page.